Construction of the Redding Tai Chi Meditation Garden (RTCMG) continues at Enterprise Park! After getting the site cleared on the first day, David Ledford and his crew at Ledford Construction and Concrete Inc. have made further progress.
The Site Takes Shape
The construction site is now fenced in, and work has begun on preparing the entrance walkway. The crew has also started laying the base material for the walkway, bringing us another step closer to seeing the garden take shape.


The entrance walkway is being carefully graded to maintain a slope of less than 5%, providing a gentle approach to the garden without the need for handrails.
If the weather cooperates, the crew hopes to begin framing the project next.
Working Around the Weather
We are still dealing with unsettled weather, with afternoon rain in the forecast. With Thanksgiving just around the corner, the crew will also be working a half day tomorrow.
As always, the schedule will depend on the weather. We will see what conditions next week bring and hope for a few more clear days to keep the project moving forward.
It is exciting to see the progress being made each day. We look forward to sharing more updates as construction continues!